Snagging

Snagging List Template and How to Close a Job Out

A free snagging list template for UK builders, what each column is for, and a process for getting a snag list to zero before handover.

Published 18 August 2026 6 min read SiteClick Team

Snagging is where a profitable job turns marginal. Items get fixed twice, get missed, or get argued about at final account. A structured list and a rule about closure fixes most of it.

The columns a snagging list needs

ColumnWhy it matters
Item numberUnambiguous reference in emails and on site
LocationRoom, plot, level, grid reference — never "upstairs"
DescriptionOne sentence, factual, no blame
Trade responsibleWho owns it
PriorityBlocks handover / before completion / defects period
Raised by and dateEstablishes when it was known
Before photoWhat the defect actually was
Target dateSomething to chase against
After photoProof of rectification
Closed date and by whomThe audit trail

The one rule that changes everything

A snag cannot be closed without an after photo. It removes the entire category of "I did that last week" and produces a complete before-and-after record for handover without any extra effort.

A close-out process that works

  1. Pre-snag internally a week before the client walk-round. Fixing your own list first halves the client's list.
  2. Walk the job with the client and record items on the spot with photos. Agreeing the list in person prevents a second list arriving by email.
  3. Distribute by trade. Each subcontractor gets only their items, with a date.
  4. Review twice a week until the list is under ten items, then daily.
  5. Issue the close-out schedule — every item with before and after photos and the date closed. Clients sign off faster when they can see the evidence laid out.

Snagging versus defects

Snags are items identified before practical completion. Defects are items arising during the defects liability period afterwards, typically six or twelve months. Keeping them on separate lists matters because they have different contractual consequences and different people paying for them.

Doing it on a phone

Paper snag lists get retyped, and things get lost in the retyping. In SiteClick a snag takes about fifteen seconds: photo, one line, trade, priority. Pin it to the uploaded floor plan so location is unarguable, and the subcontractor sees only their own list. Closure requires the after photo, and the full schedule exports as a branded PDF for handover.

SnaggingHandoverTemplates

Frequently asked questions

What is the difference between a snag and a defect?

A snag is an item identified before practical completion. A defect arises during the defects liability period after handover, usually six or twelve months.

Who pays for snagging?

The contractor or subcontractor responsible for the original work. This is why recording which trade owns each item, with photographic evidence, matters at final account.

How long should a client have to raise snags?

Typically the client raises snags at the pre-completion inspection, with the defects liability period covering anything appearing afterwards. The contract sets the exact terms.